01.04.2017

The following works are currently being carried out in the building.

The following works are currently being carried out in the building. - Kursus MMC xəbər foto

Construction works chronology for the building constructed at 22 K. Safaraliyeva Street, covering 2014-2017.

Date: 01.04.2017
External communication works are in progress.
The fire and water reservoir of the building is being constructed.
Works in the residential building are almost completed.
Residents have been allowed to start renovation works in the building.
Landscaping works around the building have started.

Date: 30.12.2016
Current status of the works related to the construction of the multi-storey residential building built by “KURSUS” LLC at 22 K. Safaraliyeva Street:
Water meters have been installed in the building.
Electricity meters have been installed.
Gas meters have been installed.
Balcony railings have been installed in the building.
Interior finishing works have been completed.
Painting of the entrance hall has been completed.
External communication works are nearing completion.

Date: 14.10.2016
Electrical works have been fully completed.
Plumbing works have been completed.
Installation of the elevator is nearing completion.
Ventilation works are nearing completion.
Installation of fire doors is continuing.

Date: 20.07.2016
Electrical installation works in the stairwells, elevator shafts and halls of the building have been completed.
Electrical and plumbing installation works in the building have been completed.
Masonry and plastering works in the mansard of the building have been completed, and overall masonry and plastering works in the building have been completed.
Installation of the elevators is continuing. Gasification works of the building have been completed.
Ventilation works in the building and basement are continuing.
Putty works in the halls have been completed.
Works on the staircases and facade cladding of the building are continuing.

Date: 01.07.2016
Masonry and plastering works on the 20th floor and mansard are nearing completion.
Roof insulation works have started.
Gasification works of the building are nearing completion.
Painting works have started in the garage section of the building.
The ventilation system has started.
Installation of the elevators has started.
Sewer risers are nearing completion.
Marble works inside the building are nearing completion.
Painting works in the stairwell and halls are nearing completion.
Works on the staircases and facade cladding of the building are continuing.

Date: 01.06.2016
Preparatory works for installing the elevators are in progress. Sewer risers are also being installed.
Electrical installation works in the stairwells, elevator shafts and halls of the building have been completed.
Installation of the building windows and facade cladding works are continuing.
Masonry and plastering works on the 20th floor and mansard are nearing completion.
Roof insulation works have started.
Gasification works of the building are nearing completion.
Painting works have started in the garage section of the building.
The ventilation system has started.
Marble works in the staircase area are nearing completion.

Date: 16.03.2016
Preparatory works for installing the elevators are in progress. Sewer risers are also being installed.
Electrical installation works in the stairwells, elevator shafts and halls of the building are nearing completion.
Installation of the building windows and facade cladding works are continuing.
Masonry and plastering works on the 20th floor and mansard are nearing completion.

Date: 19.01.2016
At present, reinforcement and concreting works in the building have been completed.
Facade works are in progress. Finishing works are being carried out on the roof covering of the building.

Date: 28.12.2015
On December 22, concreting of the mansard roof of the building was completed.
At present, formwork and reinforcement works for the roof of the stairwell and elevator shaft are being carried out.
Masonry and plastering works are being carried out on the 18th and 19th floors of the building.

Date: 23.11.2015
On October 31, concreting of the 19th floor of the building was completed.
Formwork and reinforcement works on the 20th floor are in progress.
On November 14, concreting of the 20th floor was completed.
At present, formwork and concreting works of the mansard are in progress.
Masonry and plastering works are being carried out on the 16th floor.
Facade cladding works are being carried out on the 2nd, 3rd and 4th floors.

Date: 26.10.2015
Concreting works on the 18th floor of the building have been completed.
At present, reinforcement and formwork works on the 19th floor are in progress.
Masonry and plastering works are being carried out on the 13th, 14th, 15th and 16th floors of the building.

Date: 10.10.2015
Concreting of the 16th floor of the building has been completed.
Formwork works are being carried out on the 17th floor of the building.
Concreting of the 17th floor of the building has been completed.
At present, reinforcement and formwork works are being carried out on the 18th floor of the building.
Masonry and plastering works are being carried out on the 13th, 14th and 15th floors.

Date: 02.09.2015
Concreting of the 14th floor of the building has been completed.
Reinforcement and formwork works on the 15th floor are in progress.
Concreting of the 15th floor has been completed.
At present, reinforcement works on the 16th floor are in progress.

Date: 15.08.2015
Concreting works on the 12th and 13th floors of the building have been completed.
Reinforcement and formwork works on the 14th floor are in progress.
At present, plastering works are being carried out on the 7th, 8th and 9th floors, while masonry works are being carried out on the 10th floor.

Date: 01.08.2015
Reinforcement and concreting works on the 9th, 10th and 11th floors of the building have been fully completed. Formwork and reinforcement works on the 12th floor have been completed. Preparations are underway to start concreting works on the 13th floor. In parallel with these works, masonry and plastering works are also being carried out inside the building.
At present, masonry and plastering works are being carried out on the 7th, 8th and 9th floors of the building.

Date: 01.07.2015
Reinforcement and formwork works for columns and diaphragms are being carried out on the 8th floor of the residential building.

Date: 13.04.2015
Reinforcement works for columns and diaphragms on the 6th floor of the multi-storey residential building under construction at 22 K. Safaraliyeva Street have been completed.
At present, reinforcement works for the beams and slab mesh of the 6th floor are in progress. Final preparations are being carried out for concreting the floor.

Date: 04.03.2015
Concreting works on the third floor of the residential building have been completed. At present, reinforcement and formwork works on the fourth floor of the multi-storey residential building are nearing completion.

Date: 12.02.2015
Concreting works on the second floor of the residential section of the building constructed at 22 K. Safaraliyeva Street have been completed.
After completing reinforcement and formwork works on the third floor of the multi-storey residential building, concreting works on the mentioned floor are planned to start.

Date: 26.01.2015
Concreting of the first floor of the residential section of the building has been completed.
Reinforcement, formwork and concreting works on the second floor have been completed.

Date: 26.12.2014
Concreting works on the 3 non-residential floors of the building have been fully completed.
Concreting works in the second part of the market have been completed.
Reinforcement and formwork works are being carried out on the 1st floor of the residential section of the building.
The next stage is to cover the second part of the market with a concrete layer. Concreting works are planned to be carried out at the end of the working week.

Date: 25.11.2014
In the multi-storey residential building constructed by Kursus LLC at 22 K. Safaraliyeva Street, Baku, the first part of the market has been covered with a concrete layer. Reinforcement works and, in parallel, formwork works in the second part of the market have been completed.
Foundation works for the office and residential building were carried out with high quality and successfully completed within the scheduled timeframe.
At the next stage, the foundation of the building was laid with high-quality reinforcement and concreted. The 1st floor of the parking section in the building was reinforced and concreted.
Currently, reinforcement and concreting works on the 2nd floor of the parking section are nearing completion. Preparatory works for the construction of the 1st floor of the market section of the building are also in progress.

Date: 20.10.2014
The office and residential building includes non-residential areas on the 1st and 2nd floors, an open terrace on part of the 7th floor, a two-level basement and underground parking.
The following works have currently been completed in the building:
Reinforced concrete piles with depths of 16 and 20 m were installed around the perimeter of the building. The foundation pit was excavated and a drainage system was built along its perimeter to remove groundwater. The foundation pit was filled with a 30 cm thick layer of washed crushed stone and compacted; a 10 cm thick concrete layer, two waterproofing layers and a protective concrete layer were applied on top.
Foundation works have started.
All construction works are handed over in accordance with the pre-approved work plan.